Sunday 9 November 2014

The Pink Bathroom

After, I think, five years and three months bemoaning it, we've finally demolished (as it were) the pink 'house' bathroom. Tiled lovingly from floor to ceiling in a pink rose pattern, with monolithic shower plinth, and 'cosy' loo in the corner (tucked between said plinth and the wall), it's never been much loved. The tiles were augmented with two mismatched white tiles at some date, too. Anyway, it is gone.

We started on Saturday by taking out the sink, and then took the ceiling down. It sounds drastic, but it was a false ceiling, with the 'real' ceiling hidden a couple of feet above it. We're not entirely sure why it was put in: it's got some quirkiness to it, though. The upper ceiling is higher than any of the other first floor ceilings, with a sloped section at the front/back of the house. However, the finish matches the ceiling material in the far end of the house (~15cm T&G planks)—where, in fact, the ceiling is lowest. The lower ceiling, which is at the same sort of level as the middle compartment of the house (master bedroom and landing), matched the finish there, which is a kind of long panelled effect.

We decided we had to take it down, because, oddly, the master en suite and house bathroom had the false, dropped ceiling, but the airing cupboard, between them, didn't. Because the new guest room was going to absorb the bathroom, airing cupboard, and a slice of the master en suite, the ceiling had to be consistent; and as it was, it was carried on a beam affixed to the wall we were going to take out.

Down it came, in not too horrible a fashion.

Next, we started to dismantle the walls: the walls separating the bathroom from the master en suite, and forming the airing cupboard between them, were all coming down, replaced by a new stud wall that made the en suite slightly smaller, but the soon-to-be-guest-bedroom a better size.

Eventually, by mid-morning today, we had all the walls down, generating a huge heap of cement blocks (breeze-blocks) outside the kitchen. It revealed a number of pipes and cables we'll need to sort out, that were previously hidden in the airing cupboard. We've then taken out the toilet, and attacked the shower plinth.

I described it as monolithic above, which proved unexpectedly accurate: when we took apart the tiled ply exterior, we discovered that the shower tray had been set into a three inch slab of concrete, itself held in a timber frame and on top of a foam base. Why, I have no idea. I managed to lever it up, and then break it into lumps, but it must have weighed around 200kg. In combination with the high-density cement block walls, the floor was carrying an unexpectedly enormous weight, which, to be frank, I'm glad it won't have to support any more.

By early evening, we had the contents of the room removed, now forming an absurd glacis of bagged plaster, tiles, and cement blocks outside the kitchen window, waiting an eventual skip/grabber truck plan. We then set to work stripping the plaster from the walls, with the remaining pink tiles. Eventually, we finished about ten, and the room is bare.

I'm going to try to sort out the pipes in evenings this week, and next weekend we'll insulate and plasterboard the room, and, with a little luck, start plastering first floor walls.

No comments:

Post a Comment